This Blog is intended to help Microsoft Dynamics NAV / Business Central ERP developers as well as users. If you just go through these blogs you will understand what I have told is correct. The Blog will continuously get update with latest news. This Blog is handled by a group of Microsoft Certified Partners as well as Business Solution Specialists in Microsoft Dynamics NAV and Dynamics 365 Business Central. Feel free to mail us for any doubts.

  • LS Retail
  • Help Topics
    • Finance Module
    • Manufacturing Module
    • Warehouse Module
    • Administration
  • Navision Developer
  • GST
  • D365 Business Central
  • CU Update
    • Download Business Central

SUBCONTRACTING IN NAVISION

Types of Subcontracting procedure in the Microsoft Dynamics Navision
Microsoft Dynamics NAV having mainly 2 types of Subcontracting Orders handling

Table of Contents

  • Subcontracting Order given to the out side company
    • a) Create a Subcontractor Location
    • b) Create a Vendor Card
    • c) Create Work Center
    • d) Create a BOM
    • e) Create a Routing
    • f) Create a Released Production Order
    • g) Run Subcontracting Work Sheet
    • h) Material Issue Or Sending Material to Subcontractor
    • i) Receiving Materials Or Receiving Material from Subcontractor
  • Other company given Subcontracting to Us

Subcontracting Order given to the out side company

In this type of Subcontracting we are giving partial or full material to Outside company and that company doing some work for us and finally sending the product to us. This is the most important type of Subcontracting. This procedure is as follows.

a) Create a Subcontractor Location

Create a Subcontracting Location from the Location Card

Warehouse->Setup->Locations. Fill the details as per normal Location creation procedure only difference is that you have to go to the Tax Information Tab there you select the Subcontracting Location as shown in the picture.

b) Create a Vendor Card

Vendor Card Subcontracting Order setup in Navision

Create the Subcontractor as vendor as normal procedure. After that you have to attach the vendor to Subcontracting Location from the Tax information Tab in the Vendor card. Where you have to select subcontractor, Subcontracting Location that we created just now and Commisioners Permission details. For more information see the the picture.

c) Create Work Center

This is the one of the most important area where specifying the work center area. Better you create one work center for one Subcontractor. For that go to the Work center Card from

Manufacturing –> Capacities-> Work Centers.

Work Center Card Subcontracting Order setup in Navision

In that press F3 to create a new work center and enter the information based upon your need only difference is that in the Posting Tab you have to select the Subcontractor No.

d) Create a BOM

Create Production BOM for the subcontractor from Manufacturing -> Production Design -> Production BOM. Where you specify the materials that given outside for jobwork/Subcontracting Work.

e) Create a Routing

Create a Routing from Manufacturing->Capacities->Routing. Where you specify the Work Center No. as subcontracting work center just now we created. Attch the BOM and routing no to the Item Crad, ie, in the Replenishment Tab

f) Create a Released Production Order

Create a Released Production oder from Manufacturing->Execution->Released Production Orders or MRP.

g) Run Subcontracting Work Sheet

Open the Subcontracting Work Sheet from Purchase->Order Processing-> Subcontracting Work Sheet, After that click Functions(Button)-> Calculate Subcontracts, in that window you have to specify the work center number in the Work Center Tab and Production Order in the production Order Routing Line Tab after that press Ok, to calculate the number of subcontracting lines.

Then the Subcontractor Lines will appear in the Subcontracting Work Sheet then you have to click Functions(Button)-> Carry Out Action Message. After that the Subcontracting Order will be created.

h) Material Issue Or Sending Material to Subcontractor

Material Issue on Subcontracting Order setup in Navision

Open Subcontracting Order from Purchase->Order Processing-> Subcontracting Order   You have to click Line->Order SubCon. Details Go to the Delivery Details Tab , enter Delivery component for -: as number components material you are sending Then click Function->Update Issue Details then automatically update the material to be issued. After that click Send(Button) to send the material, then system automatically create the DC for the material.

i) Receiving Materials Or Receiving Material from Subcontractor

For Receiving materials again got to the Line->Order SubCon. Details From Subcontracting Order. In that enter the Vendor Shipment No. & Posting Date. Then go to the Receipt Details tab, there enter Qty To Accept, Qty To Reject etc like information. Finally click Function-> Update Receipt Deatails to update the consumption qty lines also. Then click the Receive Button to receiving material. You can take the print of the GRN form the noramal way.

Other company given Subcontracting to Us

In this case Subcontractor giving partial or full Raw materials free of cost to us and we process some task based upon that and produce some product. Finally we sell that product to the Subcontractor with less Consignment Material.Consignment Material is that material given by the Subcontractor free of cost.

The process is as follows

  1. Create a Vendor Card for Subcontractor
  2. Create Non-Stock Item as Materials Supplied by the Subcontractor.
  3. Inward the material using Purchase Order and Warehouse Receipt.
  4. Produce the product by normal procedure.
  5. In the sales order you have to specify one more extra line as G/L account consignment as -ve entry.
  6. Better you have to design a separate Report for consignment Sales Invoice.

Reader Interactions

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Primary Sidebar

Subscribe

  • Email
  • Facebook
  • Twitter

Our Topics

Administration Analysis Reports Business Central Developer Toolkit Docker Dynamics NAV Beta Download Dynamics NAV Release Error Message Finance Module GST Human Resource Login Error LS Retail LS Retail 2013 Manufacturing Module Microsoft Certified Trainers (MCTs) Microsoft Dynamics Business Central Microsoft Dynamics NAV 2009 Microsoft Dynamics NAV 2013 Microsoft Dynamics NAV 2015 Microsoft Dynamics NAV 2017 Microsoft Dynamics NAV 2018 MSDyn365BC NAV 2016 Navision Certification Navision Developer Navision Introduction Navision Modules Navision Retail Navision Tips And Tricks Powershell Purchase Order Sales Module SQL Server Useful Sites Visual Studio Code Warehouse Module

Footer

Recent Post

  • Business Central Complete Version List and Direct Download
  • You do not have access to Microsoft Dynamics NAV or D 365 Business Central Error
  • Dynamics NAV Versions List

Search

Contact : support@navisionplanet.com for Microsoft Dynamics NAV (Navision ) and LS Retail Development or Functional support for any modules

 

Editors News Letter


New Microsoft Dynamics NAV Technical Blog opened the Navision Planet Team

MIBUTECH

https://www.mibutech.blogspot.com

Copyright © 2023 Navision Planet